Project Phasing Last Updated On:19/09/2022

 

The following table indicates the tentative phasing of the project:-

 
  1. WDFC
SN Sections Targets
1.  Rewari-Palanpur CTP - 1 & 2 Rewari-Madar (306)  Commissioned
Madar - Palanpur (353)  Commissioned
2.  Palanpur-Makarpura
 CTP - 3(R)-(289 Km)
 June 2023
Palanpur-Mahesana incl PCL (77 Km) commissioned in Jun'22
3.  Makarpura- Sachin
 CTP - 13 (135 Km)
 June 2023
 
4.  Sachin-Vaitarna
 CTP - 11 (186 Km)
 June 2023
5.  Vaitarna- JNPT
 CTP - 11 (101 Km)
Dec 2024
6.  Rewari – Dadri (Integrated Package)
 CTP - 14 (127 Km)
June 2023
Prithla-Dadri by Oct 2022
Rewari-Mewat by Dec 2022
Prithla-Mewat by June 2022
 
 
  1. EDFC
 
SN Sections Targets
1.  Khurja-Bhaupur EDFC-1 (351 Km) Commissioned 
2.  Bhaupur-DDU EDFC-2 (402 Km)  March 2023 
Rooma-Sujatpur (130 Km) commissioned
Chheoki-Chunar (110 km) by Sep 2022
3 DDU-Sonnagar(137 Km) Commissioned
4.  Khurja-Dadri EDFC-1 (46 Km) October 2022
5.  Pilkhani-Ludhiana (179 Km)  June 2023
6.  Khurja-Pilkhani (222 Km)  June 2023