Project Phasing

 

The following table indicates the tentative phasing of the project:-

 
  1. WDFC
SN Sections Targets
1.  Rewari-Palanpur CTP - 1 & 2  Rewari-Madar (306)  Commissioned
 (587 trains run)
 Madar-Marwar (143)  December 2020
 Marwar-Palanpur (204)  March 2021
2.  Palanpur-Makarpura
 CTP - 3(R)-(289 Km)
 March 2022
3.  Makarpura- Sachin
 CTP - 13 (135 Km)
 June 2022
 
4.  Sachin-Vaitarna
 CTP - 11 (186 Km)
 June 2022
5.  Vaitarna- JNPT
 CTP - 11 (101 Km)
6.  Rewari – Dadri (Integrated Package)
 CTP - 14 (127 Km)
 March -2022
 
  1. EDFC
 
SN Sections Targets
1.  Khurja-Bhaupur EDFC-1  Khurja-Bhadan (194 Km)  Commissioned
 (1276 trains run)
 Bhadan-Bhaupur (157 Km)  October 2020
2.  Bhaupur-Mughalsarai EDFC-2 (402 Km)  June 2022
3  Durgawati-Sasaram (56 Km)  Completed
4.  Balance portion of Mughalsarai-Sonnagar (81 Km)  June 2021
5.  Khurja-Dadri EDFC-1 (46 Km)  June 2021
6.  Pilkhani-Ludhiana (179 Km)  June 2022
7.  Khurja-Pilkhani (222 Km)  June 2022