Project Phasing

 

The following table indicates the tentative phasing of the project:-

 
  1. WDFC
SN Sections Targets
1.  Rewari-Palanpur CTP - 1 & 2  Rewari-Madar (306)  Commissioned
 Madar - Palanpur (353)  Commissioned
2.  Palanpur-Makarpura
 CTP - 3(R)-(289 Km)
 June 2023
(152 Km commissioned by July'22)
3.  Makarpura- Sachin
 CTP - 13 (135 Km)
 June 2023
 
4.  Sachin-Vaitarna
 CTP - 11 (186 Km)
 June 2023
5.  Vaitarna- JNPT
 CTP - 11 (101 Km)
March 2024
6.  Rewari – Dadri (Integrated Package)
 CTP - 14 (127 Km)
 December 2022
 
  1. EDFC
 
SN Sections Targets
1.  Khurja-Bhaupur EDFC-1 (351 Km) Commissioned 
2.  Bhaupur-DDU EDFC-2 (402 Km)  March 2023 
(230 Km commissioned by July 2022)
3 DDU-Sonnagar(137 Km) Commissioned
4.  Khurja-Dadri EDFC-1 (46 Km)  December 2022
5.  Pilkhani-Ludhiana (179 Km)  June 2023
6.  Khurja-Pilkhani (222 Km)  June 2023