Project Status Tabular View

1. Project in brief
a. Total length of Eastern & Western DFC
(Eastern – 1337 kms, Western – 1506 kms)
- 2843 Km (except Sonnagar-Dankuni section) Commissioned
Commissioning up to Mar.2023
Commissioning up to Jun.2023
Commissioning up to Mar/Dec.2024
b. Target - June 2024
b. Financial progress(Works) - 88 %
2. Section-wise progress
Section/Package Length Commissioning Remarks Financial Progress
WDFC
Dadri - Rewari 127 Commissioned Prithla-Dadri (52 Km) section is Commissioned 84%
Rewari - Madar 306 Commissioned Hon'ble Prime Minister Sh. Narendra Modi inaugurated Rewari - Madar section (306 Km) of WDFC on 07.01.2021. 84%
Madar - Palanpur 353 Commissioned Hon'ble Prime Minister Sh. Narendra Modi inaugurated Madar-Palanpur (353 Km) of WDFC on 18.06.2022. 84%
Palanpur - Makarpura 290 31 Dec 2023 New Palanpur- New Sanand (152 Km) section is Commissioned. Hon'ble Prime Minister Sh. Narendra Modi inaugurated New Palanpur-New Mahesana (75 Km) of WDFC on 30.09.2022 84%
Makarpura - Sachin 135 30 Jun 2023 84%
Sachin - Vaitarna 186 30 Jun 2023 84%
Vaitarna - JNPT 109 30 Mar 2024 84%
EDFC
Sahnewal - Pilkhani 179 30 Jun 2023 89%
Pilkhani - Khurja 222 30 Jun 2023 89%
Khurja - Dadri 46 Commissioned 89%
Khurja - Bhaupur 351 Commissioned Hon'ble Prime Minister Sh. Narendra Modi inaugurated Khurja - Bhaupur (351 Km) section of EDFC on 29.12.2020. 89%
Bhaupur - DDU 402 30 Jun 2023 New Bhaupur-Chunar (352 Km) section is commissioned. 89%
DDU - Sonnagar 137 Commissioned 89%