1. Project in brief
a. Total length of Eastern & Western DFC
(Eastern – 1337 kms, Western – 1506 kms)
- 2843 Km (except Sonnagar-Dankuni section) Commissioned
Commissioning up to Jun.2023
Commissioning up to Dec.2023
Commissioning up to Mar/Dec.2024
b. Target - June 2024
b. Financial progress(Works) - 88 %
2. Section-wise progress
Section/Package Length Commissioning Remarks Financial Progress
WDFC
Dadri - Rewari 127 Commissioned Dadri-Rewari (127 Km) section is commissioned. 87%
Rewari - Madar 306 Commissioned Hon'ble Prime Minister Sh. Narendra Modi inaugurated Rewari - Madar section (306 Km) of WDFC on 07.01.2021. 87%
Madar - Palanpur 353 Commissioned Hon'ble Prime Minister Sh. Narendra Modi inaugurated Madar-Palanpur (353 Km) of WDFC on 18.06.2022. 87%
Palanpur - Makarpura 290 31 Dec 2023 New Palanpur- New Sanand (152 Km) section is Commissioned. Hon'ble Prime Minister Sh. Narendra Modi inaugurated New Palanpur-New Mahesana (75 Km) of WDFC on 30.09.2022 87%
Makarpura - Sachin 135 30 Jun 2023 87%
Sachin - Vaitarna 186 30 Jun 2023 Bhestan-Sanjan (108 Km) section is commissioned. 87%
Vaitarna - JNPT 109 30 Mar 2024 87%
EDFC
Sahnewal - Pilkhani 179 30 Jun 2023 91%
Pilkhani - Khurja 222 30 Jun 2023 Khurja-Khatauli (134 Km) section is commissioned. 91%
Khurja - Dadri 46 Commissioned Khurja-Dadri (46 Km) section is commissioned. 91%
Khurja - Bhaupur 351 Commissioned Hon'ble Prime Minister Sh. Narendra Modi inaugurated Khurja - Bhaupur (351 Km) section of EDFC on 29.12.2020. 91%
Bhaupur - DDU 402 30 Jun 2023 New Bhaupur-New Ahruara Road (375 Km) section is commissioned. 91%
DDU - Sonnagar 137 Commissioned DDU-Sonnagar (137 Km) section is commissioned. 91%